Home
About Us
Our Mission And Vision
Our History
Our Team
Services
AEC Industry
Choose Us
Testimonials
Projects
Workflow
Careers
Contacts
Home
About Us
Our Mission And Vision
Our History
Our Team
Services
AEC Industry
Choose Us
Testimonials
Projects
Workflow
Careers
Contacts
Home
About Us
Our Mission And Vision
Our History
Our Team
Services
AEC Industry
Choose Us
Testimonials
Projects
Workflow
Careers
Contacts
Home
About Us
Our Mission And Vision
Our History
Our Team
Services
AEC Industry
Choose Us
Testimonials
Projects
Workflow
Careers
Contacts
Primavera P6 Scheduler Multiple Choice Questionnaire
Home
Scheduler P6
Primavera P6 Scheduler Multiple Choice Questionnaire
Primavera P6 Questions
Full Name:
Email:
Phone:
Upload CV (Max 20MB):
1. Which company developed Primavera P6?
A. Autodesk
B. Bentley Systems
C. Oracle
D. Trimble
2. In P6, what does WBS stand for?
A. Work-Based Scheduling
B. Weighted Breakdown System
C. Work Breakdown Structure
D. Weekly Build Summary
3. Which type of user-defined field can store date and time values in P6?
A. Text
B. Start Date
C. Indicator
D. Date
4. In which P6 view can you adjust the project's 'Must Finish By' date?
A. Activity Table
B. WBS View
C. Project Details
D. Resource Allocation
5. What does the 'Steps' feature in P6 help to represent?
A. Sequential activities in a project
B. Hierarchical breakdown of the project
C. Subdivisions of an activity's progress
D. Financial breakdown of a project
6. What does EPS stand for in P6?
A. Enhanced Planning System
B. Enterprise Project Structure
C. Earnings Per Schedule
D. External Planning Schedule
7. Which of these is not a default activity type in P6?
A. Start Milestone
B. Finish Milestone
C. Level of Effort
D. Duration Milestone
8. In P6, how is 'Total Float' calculated?
A. Late Start - Early Start
B. Late Finish - Early Finish
C. Early Finish - Late Start
D. Early Start - Late Finish
9. What does 'S-Curve' typically represent in P6?
A. Resource availability over time
B. Cumulative project progress over time
C. Activity durations over time
D. Cost variance over time
10. Which P6 feature enables users to try out different project scenarios without altering the main schedule?
A. Copy Project
B. Baseline
C. What-If Scenario
D. Reflection
11.Which constraint type in P6 mandates an activity to start on a particular day?
A. Must Finish On
B. Start On
C. Start No Earlier Than
D. Finish On or After
12. How can 'Resource Overallocation' be visually identified in the Resource Usage Profile?
A. Through red bars
B. With a dotted line
C. By yellow highlights
D. By blue spikes
13. Which of the following indicates the planned cost of all work scheduled to be done by a particular time?
A. Actual Cost (AC)
B. Cost Variance (CV)
C. Estimate to Complete (ETC)
D. Planned Value (PV)
14. Which of the following is NOT a type of role proficiency in P6?
A. Expert
B. Skilled
C. Proficient
D. Intermediate
15. In which P6 module can a user view portfolio performance?
A. Resource Management
B. WBS
C. Portfolio Management
D. Risk Management
16. Which field in P6 shows the difference between BCWP and BCWS?
A. CV (Cost Variance)
B. SV (Schedule Variance)
C. SPI (Schedule Performance Index)
D. CPI (Cost Performance Index)
17. How is the 'Duration Type' of 'Fixed Duration & Units/Time' characterized in P6?
A. Both activity duration and resource unit rate are flexible.
B. Activity duration is fixed; resource unit rate may change.
C. Resource unit rate is fixed; activity duration may change.
D. Both activity duration and resource unit rate are fixed.
18. Which of these is NOT a default percent complete type in P6?
A. Duration
B. Physical
C. Activity
D. Units
19. Which P6 feature provides recommended start dates for unstarted activities and expected finish dates for in-progress activities?
A. Expected Finish
B. Update Progress
C. Reschedule
D. Fill Down
20. Which of the following is a method to model the uncertainty inherent in project estimates?
A. Resource Leveling
B. Reflections
C. Monte Carlo Analysis
D. Progress Spotlighting